Welcome

The Officer Bradley A. Moody Memorial Underpass project is a roadway undercrossing in place of an existing grade crossing at Marina Bay Parkway between Regatta Boulevard and Meeker Avenue in Richmond. This grade separation project will reduce traffic congestion and allow emergency vehicles to access the South Richmond Shoreline area unimpeded. The project would improve access to proposed Water Emergency Transit Authority (WETA) ferries and improve air quality by reducing emissions of idling vehicles.

Project Funding


Contra Costa Transportation Authority, Metropolitan Transportation Commission, and the Successor Agency to the Richmond Community Redevelopment Agency.

Project Updates


Last Updated: September 25th, 2014

The Bradley A. Moody Memorial Underpass Project involves the construction of a roadway underpass on Marina Bay Parkway between Meeker Avenue and Regatta Boulevard, and is intended to resolve long-standing access limitations to the Marina Bay area caused by frequent train crossings. In early September 2013, Marina Bay Parkway was closed to traffic. This closure is planned to remain in place until early May 2015.

During the week of September 22nd, two additional concrete pours for retaining walls were completed, and all retaining wall waterproofing was completed. Additionally, rebar was placed for the last level of pump station walls, while utility relocation at the Meeker intersection with Marina Bay Parkway continued.

For the week of September 29th, crews will continuing the installation of retaining wall rebar, one retaining wall concrete pour is scheduled, and the final level of pump station walls will also be poured. Grade preparation at the Jetty/Pierson intersection with Marina Bay Parkway will continue, as will utility work at Meeker and Marina Bay Parkway.

Crews are continuing to work with PG&E to restore power to streetlights on Marina Bay Parkway south of the project. These lights utilized power from a location within the project that required demolition and are proposed to be energized by a new service to be installed as part of the project. The contractor is working with PG&E to find a way to energize the lights on an interim basis until the new service is installed.

For additional information and to be added to the project update contact list, please see the project website at www.moodyup.com.  You can also follow the project on facebook:  www.facebook.com/MoodyMemorialUnderpass, or contact the project’s public outreach coordinator Jacqueline Majors at (925) 949-6196.

Click here to view previous updates

Bulletin Board


GNB will continue working tomorrow, Saturday, September 27th. We apologize if this causes any inconvenience. 

August 21 - Like us on facebook for updates: facebook.com/MoodyMemorialUnderpass

August 14 - The completion date to have the road opened is May 2015 

Website Builder